Public Notice on the Environmental Impact Assessment for the Technological Upgrade Project of Zhejiang Tenglong Electrical Appliance Co., Ltd.’s Production Line with an Annual Capacity of 600,000 Tap Changers
Release date:
2020-08-27
In accordance with the Provisions on Public Participation in Environmental Impact Assessment, the Implementation Opinions on Effectively Strengthening Public Participation in Environmental Impact Assessment for Construction Projects, and the Notice on Standardizing the Implementation of the Public Participation System for Environmental Impact Assessment of Construction Projects,
In accordance with the Provisional Measures for Public Participation in Environmental Impact Assessment, the Implementation Opinions on Effectively Strengthening Public Participation in Environmental Impact Assessment for Construction Projects, and the Notice on Standardizing the Implementation of the Public Participation System for Environmental Impact Assessment of Construction Projects, this project must undergo public disclosure prior to the preparation of the environmental impact assessment report, so as to enable a broader range of social organizations and the general public to become informed about and participate in the project’s environmental impact assessment. The relevant details are hereby announced as follows:
I. Brief Description of the Construction Project
Project Name: Technical Renovation Project for Zhejiang Tenglong Electrical Appliance Co., Ltd.’s Production Line with an Annual Capacity of 600,000 Tap Changers
Project Type: Reconstruction and Expansion
Project Scope: Zhejiang Tenglong Electrical Appliance Co., Ltd. was formerly known as Sanmen Tenglong Electrical Appliance Co., Ltd. of Zhejiang Province. In 2010, the company relocated in its entirety to its current site and commissioned the Taizhou Environmental Science and Design Institute to prepare the “Environmental Impact Report Form for the Technical Renovation Project of Sanmen Tenglong Electrical Appliance Co., Ltd., with an annual output of 500,000 tap changers.” On July 19, 2010, the Sanmen County Environmental Protection Bureau approved the project under approval document No. Sanhuanjian [2010] No. 47. Furthermore, on October 15, 2014, the project passed the completion environmental protection acceptance inspection, with acceptance document No. Sanhuanyan [2014] No. 23.
The company currently plans to invest RMB 30 million to renovate and expand its existing plant site. The project will occupy a total area of approximately 52,136 m². It will employ the company’s proprietary tap‑changer technology and processes, procure production and testing equipment that meets domestically leading standards, and acquire domestically manufactured machinery, including machining centers, injection molding machines, hydraulic presses, vulcanizing presses, coating lines, and powder‑coating systems. Upon completion, the project will establish an annual production capacity of 600,000 tap changers.
II. Distribution of Major Environmentally Sensitive Targets within the Scope of the Environmental Impact Assessment
According to the on-site survey, the project area does not contain any protected cultural relics, historic sites, or notable ancient trees. The environmentally sensitive areas and their respective protection levels are listed in Table 1.
Table 1: Overview of Environmental Protection Sensitive Points for the Project
Environmental factors | Sensitive Point Name | With the orientation of this project | The closest distance to the project’s plant boundary | Scale | Protection Level |
Ambient air | Seaside Charm | Northwest | ~160m | Approximately 109 households | Environmental Air Quality Standard ( GB 3095-212 ) Level 2 |
Relocation housing | Northwest | ~250m | Approximately 182 households | ||
Hejia Village | S | ~260m | Approximately 100 households | ||
Galaxy Bay | Northwest | ~370m | Approximately 114 households | ||
Xiafengkeng Village | SE | ~380m | Approximately 365 households | ||
Shangfengkeng Village | SW | ~500m | Approximately 524 households | ||
Xujiatang Village | N | ~1200m | Approximately 119 households | ||
River View Flower Garden | W | ~1300m | Approximately 2,000 households | ||
Shan’ang Jiang Village | Northwest | ~1300m | Approximately 80 households | ||
Qijia Village | N | ~1500m | Approximately 120 households | ||
Hulu’ao Village | NE | ~2000m | Approximately 170 households | ||
Fanglu Village | SW | ~2000m | Approximately 100 households | ||
Wangjiacun | N | ~2000m | Approximately 120 households | ||
Heart Lake Primary School | W | ~2100m | Class 36 | ||
Oasis Villa Park | W | ~2100m | Approximately 1,000 households | ||
Lake Pond, Pleasant Colors | W | ~2200m | Approximately 200 households | ||
Xuanzhu Village | SW | ~2200m | Approximately 200 households | ||
Century Mansion | W | ~2200m | 14 high-rise buildings | ||
Shan’ao Yang Village | Northwest | ~2200m | Approximately 70 households | ||
Water environment | Zhugang Creek | N | ~310m | ~300m wide | Surface Water Environmental Quality Standard ( GB3 838-2002 ) III Class |
Acoustic environment | Seaside Charm | Northwest | ~160m | Approximately 109 households | Environmental Noise Quality Standard ( GB 3096-2008 ) 2 Class |
III. Overview of the Potential Environmental Impacts of the Construction Project
1. Waste gas
The waste gases generated by the technological upgrade project primarily include shot-blasting dust, vibratory‑polishing dust, welding fumes, Dacromet coating exhaust, Dacromet drying exhaust, powder‑coating dust, powder‑coating drying exhaust, pressing exhaust, rubber‑compounding dust, rubber‑mixing exhaust, vulcanization exhaust, injection‑molding exhaust, crushing dust, epoxy‑board cutting dust, epoxy boards, resin‑rod drilling dust, and catering‑kitchen oil‑fume exhaust. Following the treatment measures proposed in this environmental impact assessment, emissions can be brought into compliance with applicable standards.
The analysis and prediction results indicate that the project’s major pollutants will have little impact on the ambient air quality. Therefore, no atmospheric protection zone is required for the project.
2. Wastewater
The project’s wastewater primarily consists of rubber‑mixing cooling water, cutting‑spray water, and domestic sewage. The rubber‑mixing cooling water is discharged directly as clear stormwater, while the cutting‑spray water is recirculated without external discharge and requires only periodic makeup.
The project’s domestic wastewater discharge is 17 m³/d (5,100 m³/a). The project site is already connected to the municipal sewage network. Canteen wastewater is treated in an oil–water separator and then, together with other domestic wastewater, undergoes preliminary treatment in a septic tank to meet the intermediate indirect discharge limits specified in Table 2 of the Emission Standard for Pollutants from the Rubber Products Industry (GB 27632-2011). Following this, the effluent is conveyed to the municipal sewage network and ultimately discharged into Haiyou Port after being treated at the Sanmen County Urban Wastewater Treatment Plant, without causing adverse impacts on the surrounding aquatic environment.
3. Noise
During project operation, daytime noise levels at each plant boundary comply with the Class 3 standards specified in the Environmental Noise Emission Standard for Industrial Enterprises (GB 12348-2008). Following implementation of the project, and through measures such as sound insulation and noise reduction, the ambient noise environment outside the plant boundaries will remain unchanged.
4. Solid Waste
The solid wastes generated by this project mainly include metal scrap, waste emulsions, waste diesel oil, weld spatter, welding slag, DMC scrap, epoxy boards, resin‑rod scrap, baghouse dust, general waste packaging materials, hazardous waste packaging materials, spent activated carbon, and domestic waste. Metal scrap, weld spatter, welding slag, DMC scrap, epoxy boards, resin‑rod scrap, baghouse dust, and general waste packaging materials can be collected separately and sold for comprehensive utilization; waste emulsions, waste diesel oil, hazardous waste packaging materials, and spent activated carbon must be entrusted to qualified entities for safe disposal; domestic waste is collected in on‑site trash bins and then uniformly removed by the local sanitation authorities. All types of solid waste generated by this project—such as scrap, baghouse dust, general waste packaging materials, hazardous waste packaging materials, spent activated carbon, and domestic waste—are subject to appropriate treatment measures, ensuring no adverse impacts on the surrounding environment.
Upon completion, this project will, through the implementation of advanced and effective pollution control measures, ensure that emissions of all pollutants are effectively managed, thereby maintaining ambient environmental quality at its current level and complying with the principles governing environmental functional zoning.
IV. Key Measures and Strategies for Preventing or Mitigating Adverse Environmental Impacts
Table 2: Summary of Enterprise Pollution Prevention and Control Measures
Category | Pollution source | Pollutant Name | Pollution prevention and control measures | Environmental benefits |
Exhaust gas | Shot blasting process | Shot blasting dust | The shot blasting machine is equipped with a baghouse dust collector; after the shot-blasting dust is treated by the baghouse, it passes through a pipe… 15m Stack emissions ( 1# Exhaust stack). | Comprehensive Emission Standard for Air Pollutants ( GB 16297-1996 ) Secondary Standard for New Pollution Sources |
Vibratory finishing process | Vibratory polishing dust | Seal and enclose; enhance mechanical ventilation in the workshop. | ||
Welding process | Welding fumes | Enhance mechanical ventilation in the workshop. | ||
Dacromet coating process | Dacromet coating exhaust gas | A gas collection hood is installed above the mixing tank. The exhaust gases from the Dacromet coating process are collected by the hood and routed into the exhaust duct located above the baking tunnel. Within the tunnel, the exhaust gases generated during the Dacromet drying process are captured by the tunnel’s exhaust ductwork. 2 The waste gas is collected and conveyed to an activated carbon adsorption unit, where it undergoes adsorption treatment before being discharged through a single pipe. 15m Stack emissions ( 2# Exhaust stack). | ||
Dacromet Drying Process | Dacromet drying exhaust gas | |||
Powder coating process | Powder-coated dust | After being recovered and processed by the built-in plastic powder filtration device in the spray booth, it is conveyed through a pipe… 15m Stack emissions ( 3# Exhaust stack). | ||
Powder Coating Drying Process | Spray-painting and drying exhaust gas | Directly through a single 15m Stack emissions ( 4# Exhaust stack). | ||
Pressing process | Exhaust gas suppression | The hydraulic presses are arranged in a centralized layout, with a large enclosure and an induced-draft ventilation system installed above them. Air is collected by supplying cool air from below and extracting hot air from above. The exhaust gases generated during the pressing process are captured and then routed to a photocatalytic oxidation unit. + Low-temperature plasma treatment, exhaust gas passes through 1 root 15m Stack emissions ( 5# Exhaust stack). | Emission Standard for Odorous Pollutants ( GB 14554-93 ) Secondary Standard | |
Rubber compounding process | Rubber compounding dust | A fume hood is installed at the powder unpacking and feeding station; the collected exhaust gas is routed through a high‑efficiency baghouse equipped with coated filter media for dust removal, and then discharged via… 1 root 15m Stack emissions ( 6# Exhaust stack). | Emission Standard for Pollutants from the Rubber Products Industry ( GB27632-2011 ) New emission standards for atmospheric pollutants from newly established enterprises, and the “Emission Standard for Odorous Pollutants” ( GB14554-93 ) Secondary Standard | |
Mastication and open-milling processes | Rubber compounding exhaust gas | The internal mixer operates in a closed system, with localized exhaust ventilation installed at the feed and discharge ports. Above the open mill, a fume hood is provided; collected waste gases are routed to a common exhaust duct and ultimately discharged through… 1 Baghouse dust removal + After treatment by the activated carbon adsorption unit, it passes through… 1 root 15m Stack emissions ( 7# Exhaust stack). | ||
Sulfurization process | Sulfurization exhaust gas | The flat‑plate vulcanizing presses are arranged in a centralized layout, with large enclosures and induced‑draft ventilation systems installed above them. Air is collected by supplying cool air from below and extracting hot air from above. 1 Low-temperature plasma set + Treated by an activated carbon adsorption system; the exhaust gas is then… 1 root 15m Stack emissions ( 8# Exhaust stack). | ||
Injection molding process | Injection molding exhaust gas | Install suction hoses in the injection molding section; the injection molding exhaust gases are collected via the suction hoses and then directly conveyed through… 1 root 15m Stack emissions ( 9# Exhaust stack). | Comprehensive Emission Standard for Air Pollutants ( GB16297-1996 ) Secondary Standard for New Pollution Sources | |
Crushing process | Crushed dust | Individual cubicles, enclosed and sealed, with enhanced mechanical ventilation in the workshop. | ||
Epoxy board cutting process | Epoxy board cutting dust | Employ water spraying to suppress the generation of cutting dust, while enhancing mechanical ventilation. | ||
Epoxy board and resin rod drilling process | Epoxy board and resin rod drilling dust | A suction hose is installed on the side of the drilling station; drilling dust is collected via the hose and then processed by a mobile dust collector. The mobile dust collector employs baghouse filtration, and any dust that is not captured by the baghouse settles within the unit’s housing. | ||
Cafeteria | Cooking fume exhaust gas | After being treated by a medium-sized fume purification unit, the exhaust is conveyed through a fume duct to the rooftop for discharge, with a discharge height of no less than… 15m ( 10# Exhaust stack). | Emission Standard for Cooking Fume in the Catering Industry (Trial) GB 18483-2001 ) Medium-sized | |
Wastewater | Production activities | Rubber compounding cooling water | Discharge directly into the municipal sewage system. | Discharge directly as clear wastewater. |
Cutting spray water | Construct a sedimentation pond, replenish losses on a regular basis, and ensure no effluent is discharged. | Recycled and not discharged externally. | ||
Daily life | Domestic wastewater | In the short term, waste will be regularly collected and treated by the sanitation authorities; in the long term, after being treated in septic tanks to meet regulatory standards, it will be discharged into the municipal sewer system and ultimately released into the sea following treatment at the Sanmen County Urban Wastewater Treatment Plant. | Comply with the “Emission Standard of Pollutants for the Rubber Products Industry” ( GB27632-2011 ) Cousin 2 Indirect Emission Limit Values | |
Noise | Equipment operation | Equipment noise | 1 When selecting equipment, prioritize models with high precision and low operating noise. 2 Fans and other equipment generate noise through aerodynamic mechanisms; therefore, low-noise axial fans should be selected. Silencers shall be installed on the inlet and outlet ducts, with flexible connectors employed. Penetrations through walls must be tightly sealed with non-combustible materials, and appropriate sound‑absorbing and silencing measures, along with damping wraps for the exhaust ductwork, should be implemented. 3 In equipment and piping design, take measures to prevent vibration and impact in order to mitigate vibrational noise, and optimize the flow field during gas transport to reduce aerodynamic noise. In structural design, employ vibration‑damping flat tops, vibration‑damping inner walls, and vibration‑damping floors. 。 | The plant boundary complies with the “Environmental Noise Emission Standard for Industrial Enterprises” ( GB 12348-2008 ) 3 Class standard |
Solid waste | Machining process steps | Metal scrap | External sales and comprehensive utilization | Resource recovery, harmlessness, and reduction |
Machining process steps | Waste emulsion | Entrust a qualified entity with safe disposal. | ||
Milling process steps | Waste diesel oil | Entrust a qualified entity with safe disposal. | ||
Welding process | Welding tail, welding slag | External sales and comprehensive utilization | ||
DMC Pruning process | DMC Scrap material | External sales and comprehensive utilization | ||
Machining process steps | Epoxy boards and resin rod offcuts | External sales and comprehensive utilization | ||
Baghouse dust collection | Baghouse dust collection | External sales and comprehensive utilization | ||
Raw material usage | General waste packaging materials | External sales and comprehensive utilization | ||
Raw material usage | Toxic and hazardous waste packaging materials | Entrust a qualified entity with safe disposal. | ||
Waste gas treatment | Spent activated carbon | Entrust a qualified entity with safe disposal. | ||
Daily life | Household waste | Entrust the sanitation department with collection and disposal. |
V. Key Points of the Environmental Impact Assessment Conclusions Set Forth in the Environmental Impact Report Document
The technical renovation project for Zhejiang Tenglong Electrical Appliance Co., Ltd.’s production line, with an annual capacity of 600,000 tap changers, is located at No. 3 Fengming Road, Hairun Subdistrict, Sanmen County. The project will utilize existing factory facilities for production. Its construction complies with the overall urban plan and environmental functional zoning requirements of Sanmen County, and the pollutants emitted meet the national and provincial emission standards, satisfying local total‑quantity control requirements. According to the prediction results, following implementation, the surrounding environmental quality will conform to the environmental functional zoning criteria of the site. The project is consistent with the city’s master plan and aligns with national industrial policies. Moreover, upon completion, it is expected to deliver favorable economic benefits and contribute positively to local economic development.
Therefore, from an environmental protection perspective, provided that the mitigation measures recommended in this EIA are fully implemented, the “three simultaneous” system is strictly enforced to ensure compliance with emission standards, and environmental management is strengthened, the project’s implementation is feasible.
VI. Content of the Public Consultation
1. Subjects and Scope of the Public Consultation
The social organizations and local residents potentially affected within the assessment area are primarily enterprises located near the project site and the surrounding villages.
2. Period for Soliciting Comments
Public consultation period: September 21, 2018, to October 10, 2018, for a total of 10 working days.
3. Channels for Public Feedback
The public may submit their comments and views on the project construction and the environmental impact assessment (EIA) process to the project proponent and the EIA agency via telephone, letter, or in-person meetings.
VII. Contact Information for the Environmental Approval Authority, the EIA Agency, and the Project Construction Entity
1. Contact Information for the Environmental Approval Authority
Project Approval Authority: Sanmen County Environmental Protection Bureau Contact Number: 12369
2. Name and contact information of the environmental impact assessment agency undertaking the evaluation work
Environmental Impact Assessment Agency: Zhejiang Lianqiang Environmental Engineering Technology Co., Ltd. Certificate No.: National EIA Certificate Class B No. 2031
Address: No. 2, Jiahui Building, No. 181 Chaohui Road, Xiacheng District, Hangzhou
Telephone: 0571-2286727
3. Contact Information of the Project Owner
Construction Unit: Zhejiang Tenglong Electrical Appliance Co., Ltd. Address: No. 3 Fengming Road, Hairun Subdistrict, Sanmen County
Phone: 13757699090 Contact: Wu Caifei
Issuing Entity: Zhejiang Tenglong Electrical Appliance Co., Ltd.
Published on: September 20, 2018
Previous page
Previous page:
Share to
Telephone
Email box
Address
No. 3 Fengming Road, Hairun Subdistrict, Sanmen County, Taizhou City, Zhejiang Province
Website Development:China Enterprise Dynamics Nantong|Tag